12 Jun 2014A few days ago our [Director of Technology and Development] (http://www.nexus.globalquakemodel.org/author/pslh) asked me a summary of the recent developments on the engine, for the sake of reporting to the Governing Board. Since all the development at GEM is public, I thought that I would post that same report on my blog too.
I went through the [code reviews] (https://github.com/gem/oq-engine/pulls?direction=desc&page=1&sort=created&state=closed) from January 2014 up to now, to see what is “new” in the engine. In that period the engine had more than 100 pull requests (!), so I am listing here only the major changes and improvements.
-
A substantial part of the engine was removed. Lots of line of code, several database tables, and some dependencies (notably redis) were removed. We have now a code base which is much smaller and more maintainable.
-
Several delicate configuration parameters (hazard_block_size, risk_block_size, point_source_block_size, concurrent_tasks) were removed, thus reducing the burden on the final user. Now the engine is smart enough to deduce automagically the right parameters to use.
-
The distribution mechanism of the engine was unified and made more flexible. Moreover, we improved our usage of the underlying libraries (celery/rabbitmq) so that now it is possible to run hundreds of jobs simultaneously (notice jobs, not tasks)
-
The source model logic tree was decoupled from the gsim logic tree. This was a major undertaking, which allowed solving long standing inefficiencies. In particular we got huge speedups in computations with large logic trees, notably 140 times in an use case provided by one of our sponsors performing a computation with the SHARE model.
-
Huge improvements were obtained in the event based calculator. We do not store anymore multiple copies of the same rupture and we are ready to distribute the GMF computation by ruptures, with substantial performance benefits.
-
Now the sources are prefiltered according to the maximum distance before sending them to the workers, in all calculators. That helps in having more homogeneous tasks and makes a big performance improvement for site-specific analysis.
-
Area sources and fault sources are now automatically split by the engine. This also helps in producing homogeneous tasks and avoid a work that before was done manually by the hazard modelers.
-
We added support for non-parametric sources in the engine. Once non-parametric sources will be supported in nrmllib, we will be able to use them.
-
The engine server has been integrated inside the engine and its error reporting has been improved a lot. Also, the communication with the platform has been improved. Now the platform can just send a zip file to the engine server and have a computation performed.
-
The disaggregation calculator has been rewritten. Now it is is able parallelize properly, whereas before it was using a single core per site. In a real life computation (by Luis) the speedup was from 13 hours to 30 minutes.
-
Substantial steps have been taken with the goal of decoupling the computations from the database. Now in all hazard calculators (except one case) there is no direct communications between the workers and the database, everything is mediated via rabbitmq. That means that the database is less of a bottleneck that it was before, at least for small logic trees.
-
A large portion of the engine code-base has been moved into a separate repository named oq-commonlib. In particular the logic tree management has been moved there and it is now pluggable, i.e. a scientist can override the default logic tree library with its own, by following a simple API.
-
A huge amount of work went into the risk calculators. Now finally they provide results which are fully deterministic; moreover the interaction with the database has been substantially improved in terms of both speed and memory consumption (of the order of 5 times).
-
Various infrastructural improvements were implemented. For instance now the engine includes a monitor checking for the availability of the nodes and providing sensible error messages in case of crashes.
-
Hundreds of bugs were fixed.
-
Huge improvements (one or two orders of magnitude in both speed and disk space occupation) on the database side for computations with large logic trees are expected in a week or two.